Preparations for the hydraulic start-up at wastewater treatment plant in Zielona Góra

17.03.2021

Despite the pandemic, the work is in progress at the wastewater treatment plant in Zielona Góra. The installation of hydrolysis and pasteurization, which we perform as part of the extension of the sewage treatment plant, is already completed in terms of deliveries and assembly of devices. Leak tests were also carried out, electrical installations were measured and a mechanical start-up was carried out. We are currently preparing for a hydraulic start-up and soon the wastewater treatment plant will be able to enjoy new installations.